Gould Covered Patio
Click on "older posts" at the bottom of each page to see older photos.
Monday, March 31, 2014
Day 4 - March 31, 2014 - Installed final support beam against house, built scaffolding, installed ridge beam and east side rafters
Day 3 - March 30, 2014 - Installing support beams
Saturday, March 29, 2014
Day 2 - March 28, 2014 - Preparation for installation of new roof structure
Black covering is to protect from weather until work is resumed on Sunday, March 30.
Friday, March 28, 2014
March 27 - Material Delivered and Covered
Tuesday, March 25, 2014
Day 1 - March 25, 2014 - Holes dug, sonotubes placed, concrete poured in sonotubes, awning removed from deck.
Sunday, March 23, 2014
March 22, 2014